| Scheduled progress week of 09/02/2007 |
| |
| |
| Progress Week of 10/12 – 09/02 |
 |
 |
 |
|
|
|
-Parking stops have been removed. |
-Complete installation and painting of pre-cast site wall. |
-Electricians have energized elevator equipment. |
| |
|
|
 |
 |
 |
|
|
|
-IRestroom partitions have been installed on all floors. |
-Painters have sprayed hand rails in stair halls. |
-Metal stairs in stair halls have been painted. |
| |
|
|
 |
 |
|
|
|
|
-Decorative cast stone balusters have been installed. |
-Equipment for sewer main repair has been staged at the site. |
|
| |
|
|
|
| |
| Progress Week of 10/08 – 10/12 |
|
| |
Scheduled progress week of 10/15 to 10/19:
- Continue priming of the raised stucco banding.
- Begin priming the stucco body.
- Continue with ground floor electrical rough-in.
|
Average daily workforce:
* Electricians: 2
* Painters: 3
* Roofers: 5
* Supervision: 1
Total: 11 |
| |
| Notes:- |
| Drywall material has been delivered to the job site. |
| |
|
| |
| |
| |
| Progress Week of 10/01 – 10/05 |
|
| |
Scheduled progress week of 10/01 to 10/05:
- Continue roof installation.
- Begin paint finishing.
- Interior framing inspections.
|
Average daily workforce:
* Electricians: 1
* Roofers: 9
* Supervision: 1
Total: 11 |
| |
| Notes:- |
| The stair inspections are complete. |
| |
|
| |
| |
| |
| Progress Week of 9/24 – 9/28 |
|
| |
Scheduled progress week of 10/01 to 10/05:
- Complete stucco application.
- Remove scaffolding.
- Install FPL lateral from the transformer to the building.
- Load and complete roof installation.
|
Average daily workforce:
* Electricians: 1
* Fire Sprinkler Installers: 2
* Stucco Installers: 8
* Supervision: 1
Total: 12 |
| |
| |
| |
|
| |
| Progress Week of 8/27 – 8/31 |
|
| |
Scheduled progress week of 09/03 to 09/07:
- Continue sealing the windows.
- Complete the 2nd floor fire sprinkler installation.
- Begin the 3rd floor fire sprinkler installation.
- Continue the roof truss insulation.
- Continue the elevator door installation.
|
Average daily workforce:
* Mechanical: 2
* Roof Installers: 7
* Electricians: 2
* Fire Sprinkler Installers: 4
* Window Installers: 4
* Elevator Installers: 3
* Scaffolding Installers: 5
* Insulation Installers: 1
* Supervision: 1
Total: 29 |
Notes:- |
| 1. On Sept. 6th I will be meeting with Cliff Torres from the City of Greenacres Building and Zoning to review all issues surrounding the installation of the generator. |
| |
| 2. Have a great Labor Day weekend. |
| |
| |